| |
India's Power
Sector : On the way of Reform
Electricity as a subject is in
the concurrent list of constitution of India. It means that
both the Union and the State Governments can formulate policies
and laws on the subject but the responsibility of implementation
rests with the states. Distribution of electricity in particular
comes in the domain of the states.
Chiefly led by the Center, the
reforms began 1991 although at the wrong end of generation
instead of distribution of power. Perhaps this was due to
the fact that opening generation for private sector was considered
to be politically easy. In October 1991, Union Power Ministry
began to publish a series of notifications seeking to encourage
the entry of privately owned generating companies into the
electricity sector. These government orders, some of which
were later enacted in Parliament to become the Electricity
Laws (Amendment) Act of 1991, radically revised prevailing
legislation by permitting private entities to establish, operate
and maintain generating power plants of virtually any size
and to enter into long-term power purchase agreements with
SEBs. The initial government notification also provided generous
incentives to these independent power producers (IPPs), the
most noteworthy of which was a guaranteed minimum 16 percent
(repatriable) return on equity for plants that operated at
their rated capacity
for at least 6000 hours in a year, with additional bonuses
for improved capacity utilization. Other attractions for potential
investors included a five year tax holiday, a two-part tariff
(the first part covering fixed costs including the assured
return, the second covering variable costs), equity requirements
that were as low as 20 percent of project costs, and selective
counter-guarantees from the central government to cover payment
default by SEBs. The rules were clearly intended to attract
foreign private capital into the sector, because they allowed
100 percent foreign equity but insisted that Indian financial
institutions not provide more than 60 percent of the total
debt component of any given project.
From both domestic and international
investors the response to the incentives offered was
overwhelming. By mid-1995, there were about 189 offers to
increase capacity by over 75GW, involving a total investment
of over US$100 billion. Of these, 95 projects for a total
installed capacity of 48,137 MW had reached the stage of Memoranda
of Understanding (MOUs) or Letters of Intent (LOIs) with state
governments. But meanwhile, since none of the projects had
yet reached financial closure, the central government introduced
another set of carrots, granting "fast-track" status
to eight of the most promising projects and agreeing to offer
them counter-guarantees.
Overall, though, for all the excitement
with which it was launched, the reform program
turned out to be a dud: against a target of over 40,000 MW
in the period 1992-97, less than 17,000 MW were added, but
that was hardly its most controversial aspect. As we shall
see below, like the institutional impacts of lowered agriculture
tariffs and de-metering in the 1970s and 1980s, the IPP policy
of 1991 created new forms of lock-in with serious implications
for all subsequent reform
Slowly and rather painfully, the
policy makers realized that the problem lies with States and
that without comprehensive reforms in Transmission and Distribution
reforms in power sector would remain a pipe dream. Though,
reforming the transmission and distribution segments, have
been under discussion at least since 1993 when a committee
of the National Development Council (NDC) comprising six chief
ministers was set up, nothing worthwhile was achieved. Conferences
of chief ministers/power ministers were held in 1996, 1998,
2000 and 2001 and some of the important recommendations /
resolutions of the conferences/committees included:
Rationalisation
of tariffs through independent regulatory commissions
Adoption of
transparent policies on subsidies, acceptance of a minimum
all-India agricultural tariff
Benchmarking
of tariff at the minimum of 50 per cent of cost of supply
and agricultural tariff not to be less than 50
paise per unit
100 per cent
metering and energy audit, reduction of T and D losses through
elimination of theft and strengthening/upgradation
of sub-transmission and distribution system
Privatisation
of distribution in major / medium sized urban and semi-urban
areas
Decentralised
distribution management in rural areas.
In spite of the ritual of
holding conferences of chief ministers and power ministers
each year, the resolutions passed at these meetings remained
wish list.
|